I know I had some nightmares about installing it leading up to the big day. What if we wrecked it?” Coutts laughed.
But, of course, the installation went smoothly, using a four-person crew. With the clock ticking down to the final walkthrough before the opening of the next performance season. Coutts and his dedicated team spent four days installing the lift, all while other crews were drywalling, and the venue’s signature red carpet was being re-laid in the lobby.
“There we were, bringing in 5500 lbs of equipment, stainless steel, and glass, all while trying really hard to stay off the newly laid carpets. Want to lean your tools against the wall? Too bad, because the drywallers are there. Yes, was a little hectic, but the end result is so, so worth it!” said Coutts.